To find how much concrete you need, multiply length × width × thickness in feet to get cubic feet, then divide by 27 to get cubic yards. Add 5–10% for waste and uneven ground: a 10 × 10 ft slab 4 inches thick needs 1.23 cubic yards, or about 1.36 yd³ with a 10% allowance.
If you are buying bags instead of ready-mix, one cubic yard takes about 45 bags of 80 lb, 60 bags of 60 lb or 90 bags of 40 lb premix. The sections below show the formulas for slabs, footings and round post holes, a bag-count table and worked examples. The concrete volume calculator handles all the conversions for you.
The basic formula
Concrete is ordered by volume. In the US that means cubic yards (a “yard” of concrete); one cubic yard is a cube 3 ft on each side, or 27 cubic feet.
volume (ft³) = length (ft) × width (ft) × thickness (ft) cubic yards = volume (ft³) ÷ 27 thickness (ft) = thickness (in) ÷ 12
The most common mistake is forgetting to convert inches to feet. A 4-inch slab is 0.333 ft thick, not 4. If you prefer metric, multiply meters to get cubic meters; 1 yd³ = 0.7646 m³.
Bags of concrete per cubic yard
Premixed bags list their yield on the label. Typical yields for standard concrete mix are about 0.30 ft³ for a 40 lb bag, 0.45 ft³ for 60 lb and 0.60 ft³ for 80 lb. High-strength and fast-setting mixes can yield slightly less, so check the bag.
| Bag size | Yield per bag | Bags per ft³ | Bags per yd³ |
|---|---|---|---|
| 40 lb | 0.30 ft³ | 3.33 | 90 |
| 60 lb | 0.45 ft³ | 2.22 | 60 |
| 80 lb | 0.60 ft³ | 1.67 | 45 |
bags = volume (ft³) ÷ yield per bag (ft³) → always round up
Bags make sense for small jobs: setting posts, a pad for an A/C unit, steps or repairs. Above roughly one cubic yard — 45 bags of 80 lb, or 3,600 lb of material to lift and mix by hand — ready-mix delivery is usually faster and gives a more consistent pour.
Slab thickness and coverage
This table shows how far one cubic yard goes at common slab thicknesses, and how much you need for every 100 square feet:
| Thickness | Area per yd³ | yd³ per 100 ft² | Typical use |
|---|---|---|---|
| 3.5 in | 92.6 ft² | 1.08 | Walkways, shed floors on good base |
| 4 in | 81 ft² | 1.23 | Patios, sidewalks, garage floors (cars) |
| 5 in | 64.8 ft² | 1.54 | Driveways, hot tub pads |
| 6 in | 54 ft² | 1.85 | Driveways for heavy trucks, RV pads |
| 8 in | 40.5 ft² | 2.47 | Heavy equipment, thickened edges |
Going from 4 to 6 inches adds 50% more concrete, so pick the thickness the job really needs. For driveways specifically, the concrete driveway calculator includes thickness guidance.
Worked examples
1. Patio slab: 10 × 10 ft, 4 in thick
10 × 10 × (4 ÷ 12) = 33.33 ft³ 33.33 ÷ 27 = 1.23 yd³ with 10% waste: 1.23 × 1.10 = 1.36 yd³
Order 1.5 yd³ of ready-mix (most suppliers sell in quarter- or half-yard steps). In bags: 33.33 × 1.10 = 36.7 ft³, which is 61.1 → 62 bags of 80 lb, 82 bags of 60 lb or 123 bags of 40 lb — a strong argument for a truck.
2. Larger patio: 12 × 16 ft, 4 in thick
12 × 16 × 0.333 = 64 ft³ = 2.37 yd³. With 10%: 2.61 yd³, so order 2.75 yd³.
3. Two-car driveway: 20 × 24 ft, 5 in thick
20 × 24 × (5 ÷ 12) = 200 ft³ = 7.41 yd³. With 10%: 8.15 yd³. Most ready-mix trucks carry 8 to 10 yd³, so this fits a single load if you order 8.25–8.5 yd³.
4. Continuous footing: 40 ft long, 16 in wide, 8 in deep
40 × (16 ÷ 12) × (8 ÷ 12) = 40 × 1.333 × 0.667 = 35.56 ft³ 35.56 ÷ 27 = 1.32 yd³ → with 10%: 1.45 yd³
Footing trenches are rarely perfectly square, so 10% is a minimum here. The concrete footer volume calculator handles multiple footing runs, and the trapezoidal footing calculator covers sloped-side footings.
Round holes: posts, piers and columns
For cylinders, use the area of a circle instead of length × width:
volume (ft³) = π × (diameter ÷ 2)² × depth (diameter and depth in feet)
Fence post example: a 10-inch-diameter hole, 36 inches deep. Radius = 5 in = 0.4167 ft, so π × 0.4167² × 3 = 1.64 ft³ per hole — about 2.7 bags of 80 lb. A 4 × 4 post (actually 3.5 × 3.5 in) set the full depth displaces about 0.26 ft³, bringing it down to 1.38 ft³, or 2.3 bags. Budget 3 bags of 80 lb per hole; for eight posts that is 24 bags.
| Hole size | Volume | 80 lb bags |
|---|---|---|
| 8 in × 24 in deep | 0.70 ft³ | 1.2 (buy 2) |
| 10 in × 36 in deep | 1.64 ft³ | 2.7 (buy 3) |
| 12 in × 42 in deep | 2.75 ft³ | 4.6 (buy 5) |
Bag counts are for empty holes; subtract the post volume if you want a tighter number. For round deck or porch piers, sonotube forms use the same formula. Stepping stones and round pads follow the same math — see the circular stepping stones calculator.
Steps and other shapes
Break any odd shape into rectangles, triangles and cylinders, calculate each one and add them up. Solid concrete steps are a good example. For 3 steps, 4 ft wide, with 11-inch treads and 7-inch risers, each step is a block running all the way to the ground:
bottom step: 33 in deep × 7 in high middle step: 22 in deep × 7 in high top step: 11 in deep × 7 in high side area = 7 × (33 + 22 + 11) = 462 in² = 3.21 ft² volume = 3.21 × 4 ft wide = 12.83 ft³ = 0.48 yd³
That is 21.4 bags of 80 lb mix, or 24 bags with 10% extra. (The bottom step is listed as 33 inches deep because the top step’s landing sits on the two steps below it.) For curbs and gutters use the curb and gutter concrete calculator; for block walls filled with grout, the block wall calculator.
Ordering ready-mix: what to tell the supplier
- Volume in cubic yards, rounded up to the supplier’s increment.
- Strength in psi (for example 3,000 or 4,000 psi) and whether you need air entrainment for freeze-thaw exposure.
- Slump — how wet the mix is. About 4 inches is common for slabs; ask before adding water on site, because extra water weakens the concrete.
- Access and timing: distance from the street, whether you need a pump or chute extensions, and when you will be ready. Standard specifications (ASTM C94) call for concrete to be discharged within 90 minutes of batching, so have forms, tools and helpers ready before the truck arrives.
How much extra to order
- 5% for formed slabs on a well-compacted, level base.
- 10% for most DIY slabs, footings dug in soil and anything with uneven subgrade.
- 15% or more for irregular shapes, very rough excavations or pumped pours (the pump line holds concrete).
Running short is far worse than having a little left over. A cold joint where a second load meets partly set concrete is a weak spot, and a short-load fee for a small top-up delivery often costs more than the extra yardage would have. A 1/2-inch dip in the base under a 10 × 10 slab alone adds about 4 ft³, or 0.15 yd³.
Mixing your own and other practical tips
- Mixing from scratch: a common general-purpose ratio is 1 part cement, 2 parts sand and 3 parts gravel. The concrete mix ratio calculator converts a volume into bags of cement and amounts of sand and gravel.
- Base material: slabs usually sit on 4 in of compacted gravel. Estimate it with the gravel calculator.
- Weight: normal concrete weighs about 150 lb/ft³, or roughly 4,050 lb per cubic yard. Make sure a truck can reach the pour without crossing septic tanks or soft lawns.
- Strength: 3,000 psi is typical for footings and slabs; 4,000 psi or air-entrained mixes are often specified for exterior flatwork in freeze-thaw climates.
- Local rules: footing depth below the frost line, slab thickness and rebar are set by local building codes. Check with your building department before pouring structural concrete.
Frequently Asked Questions
How many bags of concrete are in a yard?
About 45 bags of 80 lb, 60 bags of 60 lb or 90 bags of 40 lb premix, based on yields of 0.60, 0.45 and 0.30 cubic feet per bag.
How much concrete do I need for a 10×10 slab?
At 4 inches thick, a 10 × 10 ft slab needs 33.3 cubic feet, or 1.23 cubic yards. With 10% extra, order about 1.36 yd³ (1.5 yd³ in practice) or 62 bags of 80 lb mix.
How do I convert cubic feet to cubic yards?
Divide cubic feet by 27, because a cubic yard is 3 × 3 × 3 = 27 cubic feet.
How many 80 lb bags do I need per fence post?
A typical 10-inch hole 3 feet deep holds about 1.64 cubic feet, roughly 2.7 bags of 80 lb mix. Plan on 3 bags per post.